MAPLE LEAF FOODS OFFICE BUILDING
Location:  MISSISSAUGA, ONTARIO
Project Team:
Owner: Bental Developments / Maple Leaf Foods
Architect: Adamson Associates
Structural Engineer: Stephenson Engineering
General Contractor: Ellis Don Construction
Steel Fabricator: Tresman Steel Industries Ltd.
Steel Detailer:  Baseline Drafting
Steel Erector:  KC Welding
Project Description:
This office facility was made up of five floors and a mechanical penthouse. The building design consisted of structural steel columns, composite floor system, and braced structural steel frames providing lateral stability to the building. Tresman Steel supplied and installed approximately 900 tonnes of structural steel and joist for this project. Erection was completed in 8 weeks.